[maxbutton id=”2″ text=”Project Details” url=”https://kiacatherine.sg/new-launches/leedon-green-condo/project-details/”] [maxbutton id=”2″ text=”Developers” url=”https://kiacatherine.sg/new-launches/leedon-green-condo/developers/”] [maxbutton id=”2″ text=”Location” url=”https://kiacatherine.sg/new-launches/leedon-green-condo/location/”] [maxbutton id=”2″ text=”Showflat” url=”https://kiacatherine.sg/new-launches/leedon-green-condo/showflat/”] [maxbutton id=”2″ text=”Price” url=”https://kiacatherine.sg/new-launches/leedon-green-condo/price/”] [maxbutton id=”2″ text=”Floor Plans” url=”https://kiacatherine.sg/new-launches/leedon-green-condo/floorplans/”] [maxbutton id=”2″ text=”Gallery” url=”https://kiacatherine.sg/new-launches/leedon-green-condo/gallery/”] [maxbutton id=”2″ text=”Progress” url=”https://kiacatherine.sg/new-launches/leedon-green-condo/leedon-green-progress/”]
Leedon Green Progress Complete Report
Current leedon green progress report as per the official statements and content are below you can read everything from the given table. If you are wondering about when they are about to launch the project then let us give you some details got from the official website of developers. As it stated on their website that Leedon Green Progress Construction progress updated as of 1st October 2022. Estimated TOP: 4th Quarter of 2023. You can read more about the Leedon Green Project details.
Foundation Work | Reinforced Concrete Framework | Partition Walls | Roofing wall | Door and Window Frames | Carpark, Roads and Drains | TOP Obtained | Certificate of Statutory Completion Obtained | |
---|---|---|---|---|---|---|---|---|
Blk 26 | Complete | Complete | ||||||
1st – 3rd | Complete | Complete | ||||||
4th – 6th | Complete | Complete | ||||||
7th – 9th | Complete | Complete | ||||||
10th – 12th | Complete | Complete | ||||||
Show less | ||||||||
Blk 28 | Complete | In Progress | In Progress | In Progress | ||||
1st – 3rd | Complete | Complete | In Progress | In Progress | ||||
4th – 6th | Complete | Complete | ||||||
7th – 9th | Complete | Complete | ||||||
10th – 12th | Complete | In Progress | ||||||
Show less | ||||||||
Blk 30 | Complete | Complete | In Progress | In Progress | In Progress | |||
1st – 3rd | Complete | Complete | In Progress | In Progress | In Progress | |||
4th – 6th | Complete | Complete | ||||||
7th – 9th | Complete | Complete | ||||||
10th – 12th | Complete | Complete | ||||||
Show less | ||||||||
Blk 32 | Complete | Complete | In Progress | In Progress | In Progress | |||
1st – 3rd | Complete | Complete | In Progress | In Progress | In Progress | |||
4th – 6th | Complete | Complete | Complete | In Progress | Complete | |||
7th – 9th | Complete | Complete | Complete | In Progress | Complete | |||
10th – 12th | Complete | Complete | Complete | In Progress | In Progress | |||
Show less | ||||||||
Blk 34 | Complete | Complete | Complete | In Progress | Complete | |||
4th – 6th | Complete | Complete | Complete | In Progress | Complete | |||
7th – 9th | Complete | Complete | Complete | In Progress | Complete | |||
10th – 12th | Complete | Complete | Complete | In Progress | Complete | |||
Show less | ||||||||
Blk 36 | Complete | In Progress | ||||||
1st – 3rd | Complete | In Progress | ||||||
4th – 6th | Complete | |||||||
7th – 9th | Complete | |||||||
10th – 12th | Complete | |||||||
Show less | ||||||||
Blk 38 | Complete | In Progress | ||||||
1st – 3rd | Complete | Complete | ||||||
4th – 6th | Complete | Complete | ||||||
7th – 9th | Complete | In Progress | ||||||
10th – 12th | Complete |
What Is Leedon Green Launch Date?
Expected CSC: 31 March 2027 As per the project details and official statement it will be launched in 2023 but they have right to change launch details, or any other information as per their rules.
Who Is Leedon Green Main Contractor?
As the Leedon green progress report The Midas touch of Hongkong Land in elevating luxury living to unforgettable experiences will be extended to the new Leedon Green condominium in Singapore. MCL Land will renovate the previous Tulip Garden condominium into a timeless, luxury living area for discerning home purchasers in collaboration with Yanlord Land.
Any Expected Date For Leedon Green Launch Date?
It should be in Expected TOP: 31 March 2024 but company will announce asap whenever they are ready to inform people.
What’s The Leedon Green Progress Report?
As per the official website there is no report on this but we’ll update this section as soon as we get the more information
Who Is Main Developer Behind Leedon Green Project?
A much-lauded property developer that enjoys a stellar reputation across 15 cities in China, Yanlord Land Group Limited is known for creating beautiful, quality homes that do not compromise on either luxury or functionality.
Is Leedon Green A Good Buy?
If you ask us then Leedon Green is an great investment and also best time to buy as they are making fast progress. Leedon Green is situated in prime District 10, near the central precinct’s Good Class Bungalow cluster, Leedon Heights, and boasts seamless connectivity islandwide. The 638-unit development is expected to be completed in 2023. These details are enough to make decision for Leedon Green Question like Should We Buy Leedon Green Project Unit? after reading the Leedon Green Progress Report.
What Is The Leedon Green Launch Price?
Leedon Green Launch price could be S$ 2,643 – S$ 2,814.21/sqft but this is only a guess from the online market so price could be different. Leedon on Green Launch Price are different and we can only guess when something is coming so we need to wait until the update from the company. Don’t be late to book an appointment for Leedon on Green.
Leedon Green Architect?
DCA Architects Pte Ltd Singapore are the architect for the leedon green project and you will have the complete details while reading the Leedon Green Progress Report.
What Is Leedon Green Propertyguru?
leedon Green Progress report is also published on different website as well as on the PropertyGuru website. This site is providing excellent information regarding the all projects and also every Singapore Real Estate agent can be listed there so its easy to know about specific project. But KiaCatherine are focusing on more projects related to singapore, one by one in depth details.
Any Leedon Green Review For The Project?
This prestigious 3ha freehold estate will feature a mix of one- to four-bedroom types, as well as only five grand, double-storey Garden Villas. Selected three- and four-bedroom owners can also relish in the luxury of having a private lift.
Latest Updated Leedon Green Transactions?
1 room 124 S$1,208,000 – S$1,943,000 538 – 753 sqft 2 room 198 S$1,400,000 – S$2,876,000 614 – 958 sqft 3 room 144 S$1,975,000 – S$4,600,000 1356 – 1496 sqft 4 room 12 S$3,813,900 – S$6,543,000 1604 – 2680 sqft